Project Profiles
Spar Project Experience
Medusa |
| PROJECT
DATA |
| Client
|
Murphy
E&P Co. |
| Award
Date |
February
2001 |
| Completion
Date |
August
2003 |
| Location |
Gulf
of Mexico; Mississippi Canyon 582 |
| Water
Depth |
2,223 ft
|
| Hull
Type |
Truss Spar
|
| Hull
Diameter |
94 ft |
| Hull
Total Length |
586 ft |
| Hard
Tank Length |
234 ft |
| Hull
Weight |
12,822 s.
tons
|
| Mooring
Type |
10-line,
Taught Catenary
Chain-Wire-Chain |
| Risers |
6 x TTR
13 3/8” x 9 5/8”
Dual cased |
| Riser
Support System |
Buoyancy Can
|
| Topsides
Dimensions |
170’
x 170’ x 62’ |
| Topsides
Payload |
8,986 s.
tons |
| Production
Capacity |
110 MMscfd,
40 Mbopd |
| Export
Pipelines |
1 x 12”
Oil SCR
1 x 12” Gas SCR |
| |
|
|
| Project
Execution Overview |
| PMT |
SparTEC
(now FloaTEC, LLC) |
| Hull
Engineering |
J.
Ray McDermott Engineering (JRME) |
| Topsides
Engineering & Procurement |
JRME |
| Mooring
Engineering & Procurement |
JRME |
| Riser
Design & Procurement |
Mentor Subsea
( a JRM company) |
| Hull
Fabrication |
J. Ray McDermott
- Dubai Fabrication Yard |
| Topsides
Fabrication |
TNG/Harbor
Island |
| Buoyancy
Can Fabrication |
JRM TNG Fabrication
Yard (Mexico) |
| Pile
Fabrication |
JRM TNG Fabrication
Yard (Mexico) |
| Mooring
Installation |
JRM DB-50 |
| Hull
Installation |
JRM DB-50 |
| Topsides
Installation |
JRM DB-50
+ SLC 5000 |
| |
|
|
Scope/Description:
Full EPCI contract to Engineer,
Procure, Construct and Install a complete
truss spar floating production platform,
complete with topsides and workover rig.
Scope of work included:
- Project management
- Engineering and procurement
management
- Hull, Mooring System & Topside
detailed engineering design
- Procurement of all
topsides and hull marine systems equipment
and mooring system equipment and components
- Hull and topsides fabrication,
assembly, outfitting and pre-commissioning
- Installation, hook-up
and commissioning ready for hydrocarbons
Innovation/Technology:
- Turnkey EPCI contract
services
- Fast-track project schedule
and delivery
- Topsides dual barge
lift installation
- Dry trees, top tension
risers
- Offset capability for
MODU drilling
- Fatigue resistant buoyancy
can system
- Fully supports completion
and workover rig
|
| |
|
| |
Click
on images below to view larger. |
|
 |
| |
 |
| |
| |
| |
| |
|
|
Schedule:

 |
|